Installation

Монтаж внутрипольного конвектора SNC

1. Decorative grid Deco Floor
2. Concrete filling
3. Alignment stud
4. Subfloor
5. Window
6. Barb bolt
7. Finished floor

Recommended floor canal size for the San Galli convector installation: width/length = (convector’s width/length + 50 mm each side). Depth = (convector’s height + 10-15 mm).
Put the convector on the prepared flat surface, align the SanGalli convector relating to the floor using the alignment studs (alignment studs are included).
Fix 100-150 mm from the window for the efficient air circulation. Setbacks at the left and at the right (if there are any 150-300 mm each) to avoid the heat action on the wall coating (wallpaper, plaster, etc.) and for the convenience of the intra-floor convector installation.
Fix the convector bath with the barb bolts to the subfloor (incl. to the supply package).
Connect the convector to the heating system (using valves).
It is vital to form heat- and waterproof course correctly. Convector canal should be performed according to building regulations. Waterproof course same to the building’s one and heat sealing (20-50 mm depth, in order to reduce heat leakage) are required.
Install DecoFloor decorative grid.
Fill manufacturing clearance between bath and canal with concrete or sealing foam.

Монтаж внутрипольного конвектора STC

1. Decorative grid Deco Floor
2. Concrete filling
3. Alignment stud
4. Subfloor
5. Window
6. Barb bolt
7. Finished floor
8. Fan box with an air pipe

Конвектор STC монтируется так, чтобы теплообменник находился со стороны помещения, а вентилятор со стороны остекления.
Конвектор STC имеет правую (R) и левую (L) сторону подключения к теплосети.
Recommended floor canal size for the San Galli convector installation: width/length = (convector’s width/length + 50 mm each side). Depth = (convector’s height + 10-15 mm). .
Put the convector on the prepared flat surface, align the SanGalli convector relating to the floor using the alignment studs (alignment studs are included).
Fix 100-150 mm from the window for the efficient air circulation. Setbacks at the left and at the right (if there are any 150-300 mm each) to avoid the heat action on the wall coating (wallpaper, plaster, etc.) and for the convenience of the intra-floor convector installation.
Fix the convector bath with the barb bolts to the subfloor (incl. to the supply package).
Connect the convector to the heating system (using valves).
It is vital to form heat- and waterproof course correctly. Convector canal should be performed according to building regulations. Waterproof course same to the building’s one and heat sealing (20-50 mm depth, in order to reduce heat leakage) are required.
Fill manufacturing clearance between bath and canal with concrete or sealing foam.
Install DecoFloor decorative grid.